Managing Systems Related Risks in the Implementation of a Modern Mass
Transit System
Jointly organized by Power Engineering Chapter and School of ECE, National University of Singapore
|
Speaker:
|
Mr. Sim Wee Meng,
Project Director,
Land Transport Authority,
Singapore |
|
Date & time: |
Wednesday 14th July 2004, 7:00pm
(Light refreshment will be served from 6:30pm) |
|
Venue:
|
Engineering Auditorium, Block EA,
Faculty of Engineering, National University of
Singapore
5 Engineering Drive 1, Singapore 117608
Map:
http://streetdirectory.com/nus/campus.cgi?x=254&y=632&level=2 |
Outline:
The
investment in building a mass rapid transit system is huge and managing risks at
different stages of the implementation is crucial to the success of the project.
The talk will focus on procurement strategy, role of a system integrator,
managing the testing and commissioning of a multi-contracts environment, test
running of the system, working along side with the Operator during trial running
to ensure that the system is ready for revenue operation.
The experience of the North East Line which
is the world's first fully automated driverless mass transit system will be
shared to highlight the various systems related risks which were managed during
the implementation of a modern and complex railway project.
About the speaker:
Mr. Sim Wee Meng has 20 years of experience
working with the railway authority of Singapore. In 1996, he was appointed as
project manager responsible for all the electrical and mechanical works for the
Bukit Panjang LRT project and in 1998 was appointed as Project Director to
oversee the completion of the project. The project was completed in 1999 and
handed to the Operator, SLRT, for revenue operation. In 2000, he assumed the
post of Senior Project Manager responsible for all the electrical and mechanical
works on the North East Line Project. He manages 16 major E&M contracts and 30
minor contracts with a total value of approximately S$1billion. The project was
completed in 2002 and handed over to the Operator, SBST and revenue operation
commenced in May 2003. Currently he is appointed as Project Director to oversee
all the electrical and mechanical works for Circle Line Project.
Further information:
Photos
|