|
Short-Duration Power-Frequency Withstand [U £ 245 kV] Reference to IEC 60-1
- maintain test voltage for 1 min.
- during wet test, if one disruptive discharge occurs on self-restoring insulation, then repeat test to pass
- test both wet and dry conditions
- atmospheric corrections, reference IEC 60-1
[U > 245 kV] Reference to IEC 60-1
- maintain test voltage for 1 min. - dry conditions only |
Short-Duration Power-Frequency Withstand [1 kV £ U < 52 kV] and [52 kV £ U] Reference to IEC 694 |
Power-Frequency Voltage Withstand [1 kV £ U] Reference to C37.34 - dry test: maintain test voltage for 1 min. apply 75% of voltage in one step, then gradually raise the voltage over 5 - 30 sec max. - wet test: maintain test voltage for 10 sec. apply voltage as above
- dew test: maintain test voltage for 10 sec raise voltage rapidly in not more than 20 sec
- atmospheric corrections, reference IEEE 4-1978 |
|
Lightning Impulse Withstand [all voltage levels] Reference to IEC 60-1
- standard impulse: 1.2/50 m s - dry conditions only - 15 impulses each test condition and each polarity - to pass: max. 2 discharges per series allowed on self-restoring insulation, AND no discharges on non-self-restoring insulation OR to pass: - 3 consecutive impulses on each polarity and condition with no discharges. - if discharge occurs on self-restoring insulation, then 9 add'l impulses with no discharges are required to pass. |
Lightning Impulse Withstand [all voltage levels] Reference to IEC 694
|
Lightning Impulse Withstand [1 kV £ U] Reference C37.34 - standard impulse: 1.2/50 m s - dry conditions only - 3 consecutive impulses, each polarity to pass: if one discharge occurs, then 9 add'l consecutive impulses are required with no further discharges Open Gap Withstand Reference to C37.34 - same method of application as power-frequency and lightning impulse tests given above - test voltage is 100% (or 110% if required) of rated withstand to ground voltage - Bias test method also cited |
|
Switching Impulse Withstand [U > 245 kV] Reference to IEC 60-1
- standard impulse: 250/2500 m s
- both polarities
- wet tests for outdoor gear only
- insulation between poles, dry test conditions only
[no reference to determination of withstand values]
Open Gap Withstand Reference to IEC 60-1 When open gap withstand voltage is higher than phase-to-earth withstand voltage, different test methods are used.
Preferred Method: combined voltage tests
- Power-frequency voltage test: two different voltage sources, in out-of-phase conditions
- Impulse voltage test: rated impulse voltage applied to one terminal; complementary voltage from another source of opposite polarity is applied to other terminal
Alternate Method: only one voltage source
- total test voltage applied between one terminal and earth; opposite terminal is earthed
ACCEPTANCE CRITERIA: No acceptance specifications given in IEC 694 |
Switching Impulse Withstand
(General Reference to IEC 694 for dielectric tests) |
Switching Impulse Withstand [U > 362 kV] Reference to C37.34
- standard impulse: 250/2500 m s
- both polarities
- both dry and wet (per IEEE 4-1978) tests required
- withstand voltage determined by "Up-and-Down Method," per C37.34 and IEEE 4-1978
Open Gap Withstand Reference to C37.34, except:
- withstand may be tested at 100%, or 110% if req'd, of rated withstand voltage to ground
- dry conditions only
- 3 applications of switching impulse voltage
- apply switching impulse withstand voltage on one terminal and apply bias voltage of 60 Hz on opposite terminal. Timing must be such that the polarity of one voltage crest is opposite from the polarity of the voltage crest on the other terminal of the switch.
ACCEPTANCE CRITERIA: - no flashovers across open gap OR - if only one flashover occurs across the open gap, then 9 add'l consecutive impulses are applied. One flashover to ground is permitted during the 3X9 series. |
|
Partial Discharge Test Reference to IEC 270 |
Partial Discharge Test [1 kV £ U < 52 kV] No References
[52 kV £ U] No tests required for the complete HV switch. - Type test on special request by user. |
Partial Discharge Test under consideration |
|
(No References or specifications cited)
|
(No References or specifications cited) |
Corona Tests [121 kV £ U]
- non-enclosed outdoor-switches - corona plumes and spikes shall not be visible at voltages lower than 1.10 times the line-to-neutral value of rated max. voltage |
|
Dielectric Test on Auxiliary & Control Circuits Reference to IEC 1180-1
Short-duration power-frequency withstand: - test voltage is 2000 V - duration 1 min. - no disruptive discharge allowed |
Dielectric Test on Auxiliary & Control Circuits [1 kV £ U < 52 kV] Reference IEC 694
[52 kV £ U] No References |
Control Wiring Insulation Test (Under Production Tests) - 60 Hz test - 1500 volts for 1 min. OR - 1800 volts for 1 second
|
|
Radio Interference Voltage
- switch both open and closed
- only for rated voltage (U) higher than 123 kV
- apply voltage of 1.1U/Ö ` 3
- duration: 5 min.
- pass if radio interference level is less than 2500 m V |
Radio Interference Voltage [1 kV £ U < 52 kV]
Not Applicable
[52 kV £ U] Reference IEC 694, and: - tests performed by agreement between user and manufacturer
- tests may be performed on one pole
- both open and closed positions
- tests not required for rated voltages 52 kV to 100 kV
- tests not required for gas-insulated substations |
Radio-Influence Voltage
- switch both open and closed - no atmospheric corrections - apply voltage at rated power-frequency of device
(no duration or acceptable levels are cited) |